April 2020 - Framing

Image
Framing begins April 2020 Rec Room and Guest Suite are taking shape Basement Top of Garage comes off to make room for the master Mountain view we will have from the 2nd floor City view we will have from the back 2nd floor

March - Concrete is poured

Image
March 2020:  Concrete is poured & inside demo! Basement concrete walls and floors in! Inside demo work: before: Kitchen before walls are demo'd after: View from Garage into upper and lower levels View into the laundry room View from entry into main living area Downstairs bath / bedroom before:  after:

Feb 2020 Basement and Guest Suite

Image
February 2020:  Basement and Guest Suite

Excavation!

Image
Excavation of the backyard and the basement work begins Nov 2019 - Jan 2020